City staff warn a school at the 72nd Street complex could delay the project for years

A commissioner wants to explore a charter or private school inside the planned North Beach pool, library and park complex. Staff say redesigning it now could push back a 2029 finish and raise costs.

A bronze historical plaque describing the Biscayne House of Refuge, with a relief of the station building
File photo: A city plaque on 72nd Street in North Beach marks the site of the Biscayne House of Refuge, in 2019. Photo: MosheA / CC BY-SA 4.0, via Wikimedia Commons

Miami Beach’s administration is urging the City Commission not to add a charter or private school to the 72nd Street Community Complex, the North Beach pool, library and park building voters funded in the 2018 general obligation bond. Doing so now could delay the project by years and expose it to rising costs, according to a memo on the commission’s Wednesday, Nov. 18 agenda.

The idea comes from Commissioner David Suarez, who first referred it to the Land Use and Sustainability Committee in May 2025. His referral memo said residents and would-be residents had raised concerns about a shortage of schools in the city. The committee heard staff’s assessment on April 1, 2026, and sent the item to the full commission, where it has gone unheard at five meetings since May 20, the clerk’s notes show.

The planned complex includes a 500-space garage, a 50-meter competition pool, a 25-meter pool, a 7,500-square-foot county library, a community center, a fitness center, retail space, about 60,000 square feet of green space, a jogging path and rooftop pickleball courts. The Design Review Board approved the design in May 2025, with the façade artwork and site changes approved in April and July 2026.

Staff expect the design to be 90% finished by early 2027, a guaranteed maximum price set in summer 2027, and construction from late summer 2027 to late summer 2029. Adding a school, the memo says, would mean finding an education partner and negotiating an agreement, paying the architect, Wannemacher Jensen Architects, and the construction manager for redesign, possibly returning to the Design Review Board, and taking the plan back to residents and the city boards that already backed it.

The memo puts the fiscal impact as “to be determined” and points to the commission’s direction to budget at the rolled-back tax rate, which it says could require up to $25 million in cuts, and to state proposals to cut property taxes, which provide 62% of the city’s general fund. If the commission wants a school, the capital plan would have to be amended, staff wrote.

The commission meets at 8:30 a.m. Wednesday at City Hall, 1700 Convention Center Drive. Earlier coverage of a related item on the North Shore Community Center’s future is here.