Muss Park drainage fix won't start construction until mid-2028, city schedule shows

The Chase Avenue and 44th Street project would replace a temporary emergency pump with a permanent pump station, but building it is set for June 2028 to August 2029.

Map showing the location of Muss Park in Miami Beach
Muss Park, site of the planned stormwater pump station project. Photo: Red Sidewalks; map data © OpenStreetMap contributors / Red Sidewalks original; map data ODbL, via Red Sidewalks map

Construction on a new pump station and drainage system for the blocks around Muss Park in Mid-Beach is not expected to begin until June 2028, according to the schedule the city’s engineers showed at a public meeting Tuesday, Nov. 17. The schedule puts substantial completion in August 2029.

The project, listed as Critical Needs Project #2 in the city’s 2024 Stormwater Master Plan, covers Muss Park, Chase Avenue and West 44th Street in the Nautilus neighborhood. The city sent residents a recap of the meeting, with the presentation and a recording, on Friday.

What’s there now

According to the presentation by the engineer of record, 300 Engineering Group, the area drains through 16 catch basins, six manholes, about 850 feet of pipe and about 625 feet of exfiltration trenches, which let stormwater soak into the ground through gravel-wrapped perforated pipe. The presentation says those trenches can’t hold enough water because the water table is high, and that king tides push groundwater up and shrink their capacity further.

The city now relies on a temporary emergency pump and an above-ground treatment system before water goes out an outfall into the Biscayne Waterway, the presentation says. Replacing that with a permanent system is one of the project’s main goals.

The plan

The design removes the exfiltration trenches and adds catch basins, manholes and larger solid pipe, a permanent water-quality structure meant to remove solids, oil, grease and nutrients, a pump station with above-ground electrical equipment and emergency overflows to the outfall, and a new control structure before the outfall. A new access point at Muss Park would let crews maintain the equipment.

Why it takes so long

Permits come first. The presentation lists a county environmental (DERM Class II) permit and a county sewer relocation permit as awaiting answers to requests for more information, city building permit and Design Review Board reviews as started, and state water-management and dewatering permits not yet submitted. The schedule allows until April 2027 for permits and the Design Review Board, bids from May to August 2027, a commission contract award by Sept. 30, 2027, and contract, bonding and preparation work through June 2028.

Questions go to Mid Beach Neighborhood Affairs Coordinator Gabriella Gonzalez at [email protected]. The schedule is the city’s estimate, and the presentation says bidding may start earlier depending on the permit agencies’ comments.

Red Sidewalks reported on the meeting notice Nov. 3.