With no debate and no public speakers, city moves North Beach CRA's unspent $5.5 million into this year
The Nov. 18 votes nearly double the agency's budget to about $10 million. Commissioners also approved half-plaza shade sails at Normandy Fountain, paid for by the CRA.
The Miami Beach City Commission and the North Beach Community Redevelopment Agency board voted Nov. 18 to carry about $5.5 million the agency didn’t spend last year into this year’s budget. Nobody from the public spoke, and commissioners asked one question.
That’s according to the meeting’s transcript. The commission, which also sits as the agency’s board, first approved the two budget amendments as City Commission items R7 B and R7 C. It then recessed, met as the agency, and passed the same changes as items CRA-1 and CRA-2. The clerk announced each agency vote as approved 7-0. The minutes haven’t been posted yet.
What the vote does
A city budget official told commissioners the amendments recognize “a projected surplus of 5.5 million dollars” at the end of fiscal 2026 and move all of it into 2027 “so those funds could be used in 27 if needed,” according to the transcript. The only question from the dais was how much money was moving.
The agenda memos show what that means for North Beach. The agency spent $685,265 of its $6,035,000 budget in the year that ended Sept. 30. Lines for small businesses, beautification grants and the arts were cut to a fraction of plan, and $5,485,000 carries forward. That nearly doubles this year’s budget, from $4,465,000 to $9,950,000. Most of the carryover sits in two reserves: $2,430,000 for affordable and workforce housing and $4,902,800 for future projects, as Red Sidewalks reported before the vote. The amendments set no new projects for the money. The agency is still writing its five-year plan for how to spend it.
Shade sails for two-thirds of the plaza
Earlier the same day, commissioners approved item R7 K on a voice vote, scaling back the shade sails at Normandy Fountain Plaza to a single phase over the north section. Commissioner David Suarez asked why the cost had grown. Capital Improvement Projects Director David Gomez said the original proposal changed once structural engineering was done, and the first phase fits the budget of just under $100,000. Gomez said Phase 1 covers about two-thirds of the plaza. He said a second phase would cost about $150,000 more, and that “the community has elected not to pursue” it, according to the transcript. The CRA pays for the project, which the agency’s October presentation lists among its “investments so far.”
What’s next
The agency’s advisory committee met Nov. 10 on the five-year plan. Neither the city nor the agency has posted a presentation or minutes from that meeting, and Red Sidewalks will report on it once a record is available. The agency’s documents are on its website.